9/07/2017

A320neo deliveries

Reuters reports that August (as well as full year) deliveries for the A320neo are disrupted by slow deliveries of PW's PW1100G. The goal is to deliver about 200 A320neo this year, only 78 have been delivered by the end of August.
That deliveries with the PW1100G are slow and delayed is not particulary new. Not mentioned in the article though is the fact that alos deliveries with CFM's LEAP-1A slowed down in the last two months. After delivering 10 A320neo with the LEAP-1A in June, there were 6 in July and 7 in August. For the PW1100G the numbers are 1 for June,  3 in July and 3 in August.
An indication for future delivieries is are the numbers of first flights with the respective engines:
In June 12 A320neo with the LEAP-1A made their first flights, then 5 in July and only 3 in August.
For the PW1100G the numbers are 0 in June, 4 in July and 8 in August.
So it looks like the situation at PW gets (at least) a little bit better, but worse for CFM.

No comments:

Post a Comment